How is a late-stage viability review payment calculated?

The review shares the upside of a scheme consented below the affordable housing target, and it never shares the downside.

A late-stage viability review payment is a share of the surplus the scheme earns over its consented viability appraisal: the rise in GDV, less the rise in build costs, less the developer's profit on the extra GDV, times the authority's share, capped at the cost of the affordable housing the scheme did not provide. On an illustrative 200-home scheme whose GDV beats the appraisal by £10.0m while costs rise £3.0m, the surplus is £5.25m and the payment at a 60 per cent share is £3.15m, 45.0 per cent of the net improvement.

Worked in full in The Real Estate Development Manager by Julian R. Sterling, with every figure reproduced in a free workbook.See the book on Amazon →

When a scheme is consented below the affordable housing target because the viability appraisal said it could not afford more, the planning authority usually reserves the right to look again. A late-stage review takes place near the end of the build, once most homes are sold or let, and uses actual sales values and actual costs. In London the Mayor's 2017 Affordable Housing and Viability Supplementary Planning Guidance set a widely copied form: commonly a review at 75 per cent of sales, a 60:40 split of the surplus in the authority's favour, and a cap at the policy-compliant level. Elsewhere the trigger, share and cap are whatever the section 106 agreement says, so read it before modelling it.

The assumptions

An illustrative build-to-sell scheme, £ million. Values, costs and the per-home deficit are assumptions.
InputValue
Homes200
GDV in the consented viability appraisal120.0
Build costs in the consented appraisal80.0
GDV at review, actual sales plus valuation of unsold homes130.0
Build costs at review, actual plus cost to complete83.0
Developer's profit agreed in the appraisal, % of GDV17.5%
Authority's share of surplus60%
Affordable housing provided / policy target20% / 35%
Deficit per affordable home not provided (market value less transfer value)0.25

The land value is not reopened. It stays at the benchmark used in the original appraisal, which is why the formula only looks at changes in GDV and build costs.

The calculation, step by step

Step 1: the changes

Change in GDV = 130.0 − 120.0 = 10.0, or 8.33 per cent

Change in build costs = 83.0 − 80.0 = 3.0

Step 2: the developer's profit on the extra GDV

P = 10.0 × 17.5% = 1.75

Step 3: surplus and payment

Surplus = ΔGDV − ΔCosts − P = 10.0 − 3.0 − 1.75 = 5.25

Payment = 60% × 5.25 = 3.15

Step 4: the cap

Homes short of target = 200 × (35% − 20%) = 30; cap = 30 × 0.25 = 7.50. The payment of 3.15 is below it.

Excel: =MIN(MAX(0,(dGDV-dCost-dGDV*Profit))*Share, Units*(Target-Provided)*Deficit)

The result: who keeps the improvement

The scheme is 7.00 better than the appraisal assumed: 10.0 more revenue, 3.0 more cost. The authority takes 3.15, enough for about 12.6 affordable homes at the assumed deficit, usually paid as a contribution to off-site provision. The developer keeps 3.85, 55.0 per cent, made of its 1.75 of profit on the extra GDV and 40 per cent of the surplus, 2.10.

Measured against the rise in revenue alone, the review takes 31.5 per cent of the 10.0 rise in GDV. At the margin it takes more: once the cost increase and the profit deduction are covered, each extra pound of GDV pays 49.5 pence to the authority until the cap binds. That is the number to put in the developer's appraisal next to the sales risk: upside is shared, downside is not.

What if sales values come in differently?

£ million. Build costs 83.0 at review in every row; cap 7.50.
GDV changeGDV at reviewSurplus60% sharePayment after capDeveloper's change in profit
−5.00%114.00−7.950.000.00−9.00
0.00%120.00−3.000.000.00−3.00
5.00%126.001.951.171.171.83
8.33%130.005.253.153.153.85
15.00%138.0011.857.117.117.89
25.00%150.0021.7513.057.5019.50

Two thresholds frame the table. With costs up 3.0, a payment starts only once GDV rises more than 3.64, 3.03 per cent, because the cost overrun and the profit on the extra revenue are deducted first. The cap binds once the surplus reaches 12.50, which takes a GDV rise of 18.79, 15.7 per cent. Above that, the developer keeps every extra pound again.

Below the appraisal, nothing flows back. A scheme that sells 5 per cent under its appraisal loses 9.00 of profit and the review does not refund any of the affordable housing already provided. The review is a one-way option held by the authority, and a developer pricing land should value it as one: on a probability-weighted range of outcomes rather than at the base case, where it is often assumed to cost nothing.

The common mistakes

Takeaway

Payment = min(share × max(0, ΔGDV − ΔCosts − profit × ΔGDV), homes short of target × deficit per home). Here 60% × 5.25 = 3.15, well under a 7.50 cap. The mechanism is close to an overage on a land sale, with the authority as the beneficiary, and its cap is the same per-home deficit that drives how affordable housing reduces residual land value. The residual appraisal and the quarterly cash flow behind both are in the free workbook for this case.

Questions readers ask

When does a late-stage viability review happen?

Typically near the end of the build, once a set share of homes has been sold or let; the London guidance uses 75 per cent. Actual sales values and evidenced costs then replace the appraisal figures. In the illustrative case a quarter of the 130.0m GDV is still a valuation of unsold homes at that point, which is where most review disputes start.

Is a late-stage review payment capped?

Usually, at the cost of providing the affordable housing the scheme fell short of the policy target. In the illustrative scheme 30 homes are short of a 35 per cent target at a deficit of 0.25m each, so the cap is 7.50m. It binds once GDV rises by 15.7 per cent over the appraisal with costs up 3.0m.

What share of the surplus does the council take?

Whatever the section 106 agreement says. London's widely used form gives 60 per cent to the authority and 40 per cent to the developer. On a 5.25m surplus that is 3.15m and 2.10m; with its 1.75m profit on the extra GDV, the developer keeps 55.0 per cent of the 7.00m net improvement.

Read the whole case

This article is one calculation from The Real Estate Development Manager. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.

Get the book on Amazon →Free companion files

Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada

Also on this site

Reading guide: real estate investing, finance and fund management → · All 1706 articles →

If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.