Full 20-year capital stack, Section 6418 transferability, IRC Section 50(c) MACRS math, and the 1,407 bps FEOC stress test.
Under the One Big Beautiful Bill Act (OBBBA) and IRS Notice 2026-15, losing IRC Section 48E ITC eligibility to FEOC or MACR supply-chain rules collapses LDES levered equity IRR by over 1,400 basis points. Here is the complete capital-stack math.
In The Long-Duration Energy Storage Handbook, Ironwood Storage Holdings, LLC finances Ironwood Multi-Day Storage Park ($250,000,000 CapEx, $268,876,923 total uses including $12,000,000 IDC/fees and $6,876,923 six-month DSRA) using three capital pillars:
If Chinese vanadium precursors or Prohibited Foreign Entity (PFE) inverters trip the OBBBA Material Assistance Cost Ratio (MACR) under IRS Notice 2026-15, Ironwood loses $86,400,000 of cash proceeds, forcing sponsor equity up +$86,400,000 to $132,424,874 and collapsing levered IRR by 1,407 bps down to 0.74 percent. Similarly, leasing $90,000,000 of vanadium electrolyte at 7.50 percent in a U.S. 40 percent ITC project forfeits $32,400,000 of net ITC cash and cuts Year-1 CFADS by $6,750,000 unless the lessor captures and passes through the tax credit.
Compare LCOS across all four LDES technologies in LDES revenue stacks, ELCC capacity accreditation, and LCOS, structure bankable offtakes in LDES offtake contracts, tolling agreements, and UK Cap-and-Floor, and stress-test FEOC and debt rates live in the free LDES Project Finance and LCOS Model (Excel).
Yes. Unlike wind and solar which faced accelerated phase-outs under the July 2025 One Big Beautiful Bill Act, standalone energy storage (>= 5 kWh) retained its Section 48E runway (30 percent with PWA plus 10 percent Energy Community/Domestic Content adders) and Section 6418 cash transferability, subject to strict FEOC/PFE and IRS Notice 2026-15 MACR compliance.
IRC Section 50(c)(1) requires reducing depreciable MACRS tax basis by 50 percent of the allowable ITC. On Ironwood's $240 million eligible basis with a 40 percent ($96 million) ITC, depreciable 5-year MACRS basis drops by $48 million to $192 million.
On Ironwood Multi-Day Storage Park, losing the 40 percent Section 48E ITC wipes out $86.4 million of net Section 6418 cash proceeds, jumping sponsor equity from $46.02 million to $132.42 million and collapsing 20-year levered IRR by 1,407 bps from 14.81 percent down to 0.74 percent.
This guide is drawn from The Long-Duration Energy Storage Handbook, following utility-scale and industrial LDES projects from decoupled cost physics through FERC Order 2023, PJM ELCC, power tolling, UK Cap-and-Floor, Section 48E FEOC compliance, and sculpted debt.