Section 45Y Bonus Adders, PWA Cure Penalties, Domestic Content, and OBBBA PFE Rules

Navigating T.D. 9998 ($140,485.50 cure vs. $13,797,000 at risk), Notice 2025-08 (50.0 percent), Notice 2026-15 MACR (40.0 percent), and Oregon Env. Council v. IRS.

Missing Prevailing Wage and Apprenticeship slashes Section 45Y credits by 80 percent, while missing the new OBBBA Material Assistance Cost Ratio (40 percent in 2026) destroys 100 percent of the credit. Here is the practitioner playbook for T.D. 9998, Notice 2025-08, Notice 2026-15, and Oregon Environmental Council v. IRS.

Worked in full in The Section 45Y Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

PWA Cure Math (T.D. 9998) and Notice 2025-08 Domestic Content

As modeled in The Section 45Y Handbook, Red Mesa Wind I logs 220,000 construction labor hours (requiring 33,000 qualified apprentice hours at 15.0 percent). If a post-COD payroll audit finds 18 workers underpaid by $6.50/hr across 400 hours each, curing the error costs $140,485.50 standard ($46,800 back wages + $3,685.50 interest at AFR + 6% + $90,000 IRS penalty) or $331,456.50 for intentional disregard, protecting $13,797,000 of Year 1 Section 45Y credits (a 98-to-1 return on cure cost).

For the +10 percent Domestic Content bonus (IRC Section 45Y(g)(11)), projects beginning construction in 2026 must certify 100 percent U.S. melted-and-poured structural steel/iron AND clear a 50.0 percent manufactured product threshold (rising to 55.0 percent in 2027+). Using Notice 2025-08 safe harbor tables, Red Mesa Wind I scores 54.0 percent (+4.0 percent cushion).

OBBBA Prohibited Foreign Entities (Notice 2026-15) and BOC Cutoffs

OBBBA / PFE Compliance Gate2026 Statutory RuleRed Mesa Wind I Result
Material Assistance Cost Ratio (MACR)Non-PFE direct costs >= 40.0 percent (55% EST)Base 55.0 percent (PASS) vs. 37.5 percent (100% FAIL)
Wind & Solar Placed-in-Service CliffPIS <= Dec 31, 2027 unless BOC <= Jul 4, 2026May 2026 BOC / Oct 2026 PIS (Safe)
Beginning of Construction Safe HarborOregon Env. Council v. IRS vacated Notice 2025-42Belt-and-Suspenders (Physical + 5% SH)
Non-Wind/Solar Phase-Down (Geothermal/Nuclear)100% through 2033; 75% (2034); 50% (2035); 0% (2036)Prairie Municipal Geothermal Facility 2027 BOC fully eligible

Check the 45Y vs. 48E math in Section 45Y credit rates and the 45Y vs. 48E election, compare monetization channels in Section 6418 transferability, Section 6417 Direct Pay, and partnership flips, and test your project's MACR buffer in the free Section 45Y Credit and Monetization Calculator (Excel).

Questions practitioners ask

What is the 2026 Material Assistance Cost Ratio (MACR) threshold under OBBBA and Notice 2026-15?

For Section 45Y and 48E qualified generating facilities beginning construction in 2026, non-PFE direct material and product costs must be at least 40.0 percent of total direct costs (increasing +5 percent annually to 60.0 percent in 2030). Energy Storage Technologies face a 55.0 percent floor in 2026.

Is the 5 percent Beginning of Construction Safe Harbor still available for wind and solar projects over 1.5 MW?

Yes as of November 2026: on June 6, 2026, the U.S. District Court for the District of Columbia vacated IRS Notice 2025-42 in Oregon Environmental Council v. IRS, restoring both the Physical Work Test and the 5 percent Safe Harbor, though institutional sponsors pair both methods to hedge appellate risk.

What is the penalty for failing Prevailing Wage requirements on a Section 45Y project?

To cure a failure and preserve the 5x credit rate, the taxpayer pays affected workers 100 percent of back wages plus interest (short-term AFR + 6%) and an IRS penalty of $5,000 per worker ($10,000 and 3x back wages plus interest for intentional disregard), unless waived via prompt voluntary cure or a Qualifying PLA.

Read the full handbook

This guide is drawn from The Section 45Y Handbook, following clean electricity facilities from emissions qualification and OBBBA PFE screening through Section 45Y vs. 48E election, Section 6418 transfers, Direct Pay, and Form 7211 filing.