Book · Julian R. Sterling
A Project Controls Guide to EIA-748 Guidelines, Performance Measurement Baselines, CPI and SPI, Earned Schedule, Estimates at Completion, Variance Analysis, Integrated Baseline Reviews and DoD EVMS Compliance
Google Play Paperback, $32.99 PDF edition, $19.99
Buying for your firm? Add your company name and VAT number at checkout and they go on the invoice. For a team: team license, up to 10 people, $59.99 · firm-wide license, $139.99.
Earned value management answers the two questions a budget-versus-actual report cannot: how much work the money has bought, and what the program will cost and when it will finish. The rules changed in 2026: EIA-748 revision E with its 27 guidelines, a new DoD EVMS Interpretation Guide dated June 24, 2026, and a class deviation that resets the DoD thresholds at $50 million for a compliant system and $100 million for a system the cognizant Federal agency has accepted. Behind every index sits a baseline, a measurement technique for each work package, and a forecast someone has to defend.
The Earned Value Management Handbook works the whole discipline on one fictional contractor, Tamsfield Aerosystems, Inc., and its Corriden airborne sensor pod development contract: cost-plus-incentive-fee, target cost $112,000,000.00, eleven control accounts, a 20-month plan. At Month 12 it has BCWS $65,075,000.12, BCWP $50,152,166.24 and ACWP $56,269,156.64: CPI 0.89, SPI 0.77, 45.1 percent complete and 50.6 percent spent. The book builds the baseline and reviews it, holds a contract modification in undistributed budget, releases management reserve twice, writes the variance analysis reports, computes seven estimates at completion, weighs an over target baseline and declines it, and measures every forecast against the final cost of $125,271,350.33. A second illustration, the Pellwood Clinic, applies lighter EVM to a construction project with a guaranteed maximum price of $18,600,000.00. Every name, budget and cost is invented for illustration. Standards, guides and clauses are described as read in November 2026.
Every figure below is computed by the book's model and reproduced in the companion workbook. Tamsfield Aerosystems, Inc., the Corriden program, the Pellwood Clinic and every person in the case are fictional; budgets, costs, counts and months are invented for illustration, and the variance thresholds and incentive terms are the case contract's, not DoD values.
| Item | Value |
|---|---|
| Contract at award: target cost / target fee / contract value | $112,000,000.00 / $8,960,000.00 / $120,960,000.00 |
| Baseline at award: contract budget base / management reserve / PMB | $112,000,000.00 / $6,970,000.00 / $105,030,000.00 |
| Final baseline: contract budget base / management reserve / BAC | $116,800,000.00 / $4,540,000.00 / $112,260,000.00 |
| Month 12 cumulative: BCWS / BCWP / ACWP | $65,075,000.12 / $50,152,166.24 / $56,269,156.64 |
| Month 12: cost variance / schedule variance | -$6,116,990.40 / -$14,922,833.88 |
| Month 12: CPI / SPI / percent complete / percent spent | 0.89 / 0.77 / 45.1 percent / 50.6 percent |
| Earned schedule at Month 12: ES / SPI(t) / IEAC(t) | 9.81 months / 0.82 / 24.47 months |
| Index EACs at Month 12: at budget / cumulative CPI / composite | $117,396,990.40 / $124,852,667.80 / $145,259,769.24 |
| Bottom-up EAC / program manager EAC | $122,244,552.90 / $124,644,552.90 |
| TCPI to BAC / to the program manager EAC | 1.11 / 0.894 |
| Control accounts needing a variance analysis report at Month 12 | 8 of 11 |
| Integrated baseline review: PMB reviewed | $96,900,000.00 (92.3 percent) |
| Over target baseline rules of thumb met / decision | 2 of 4 / baseline kept |
| Level of effort cost after the LOE stopped earning | $1,701,500.00 |
| Final cost / overrun against the BAC / final CPI | $125,271,350.33 / $13,011,350.33 / 0.90 |
| Fee earned / below target fee | $6,802,594.90 / $2,541,405.10 |
| Pellwood Clinic at Month 7: CPI / SPI / EAC by CPI | 0.95 / 0.83 / $18,042,844.83 |
The live Excel files behind every table in the book. Blue inputs, black formulas, no macros, and a Checks tab that must read zero. No sign-up required for book readers.
Appendix A, chapters 1 to 17
Twenty-two tabs: README, Inputs, Baseline_Log, PMB_Time_Phased, Earned_Value, Actual_Cost, Program_Monthly, CA_Status_M12, Techniques, Subcontract, Earned_Schedule, EAC_Methods, Bottom_Up_EAC, TCPI, VAR_Thresholds, IBR, Schedule_Health, OTB_Test, Fee, Withholding, Pellwood and Checks. BCWS, BCWP and ACWP rebuilt by work package and month from each technique, the baseline log, the monthly program indices, the Month 12 control account status, the LOE distortion, the subcontract roll-up, earned schedule, the five index EACs at Months 6, 12 and 18, the bottom-up and program manager EACs, TCPI, the variance tests, the baseline review, schedule health, the over target baseline tests, fee, the withholding what-if and the Pellwood Clinic.
Download EVM_Workbook.xlsx172 KBStandalone practitioner tool
Enter the BAC, an optional management reserve, the planned duration and monthly PV, EV and AC for up to 36 months. Read CV, SV, CPI and SPI, cumulative and current, the EAC by four methods with the VAC of each, TCPI, earned schedule, SPI(t) and IEAC(t), and a flag when an EAC exceeds BAC plus reserve. Prefilled with an illustrative Example Project.
Download Earned_Value_Calculator.xlsx17 KBWant the calculator first? Open the free Earned Value Calculator page for what it computes and the Excel download.
Project controls engineers and analysts, control account managers, program and project managers, program finance staff, the EVM teams of DoD, NASA and other agency contractors and their subcontractors, and owners and contractors who run construction or engineering projects on earned value.
The 27 guidelines of EIA-748 revision E and the June 24, 2026 DoD EVMS Interpretation Guide, when EVM is required under Class Deviation 2026-O0011 and its Revision 1 (the $50 million and $100 million thresholds) and the FAR, the WBS, OBS and control accounts, earned value techniques, the performance measurement baseline, integrated baseline reviews, CV, SV, CPI and SPI, earned schedule, estimates at completion and TCPI, variance analysis reports, the IPMDAR, baseline changes, over target baselines, surveillance and withholding, and lighter EVM for commercial and construction projects, all as read in November 2026.
Yes. One fictional contractor runs a $112,000,000.00 target cost development contract through every chapter: eleven control accounts, a baseline review, a contract modification, two management reserve releases, a Month 12 status at CPI 0.89 and SPI 0.77, seven estimates at completion, and the final cost of $125,271,350.33.
Yes. The 22-tab workbook and the standalone Earned Value Calculator are free on this page, with no sign-up for book readers.
No. The book explains the standard, the DoD guidance and the clauses as read in November 2026. Thresholds, clauses and data items change, and your contract, your contracting officer and your counsel decide what applies to your program.
Related titles. Full list on the author page.