Quantitative VfM ($53,968,725 / 6.4 percent savings), $286,602,981 GASB 94 liability, IRC Sec. 142(a)(5) PABs, and Rev. Proc. 2017-13.
A wastewater DBFOM P3 pays higher private financing spreads than municipal bonds and books a full GASB 94 balance-sheet liability. Here is the exact Quantitative Value for Money (VfM) and IRC Section 142(a)(5) PAB math showing when P3 risk transfer actually saves ratepayers money.
Worked in full in The Wastewater Treatment Project Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
In The Wastewater Treatment Project Finance Handbook, Cedar Creek Water Partners, LLC delivers the $240,000,000 Cedar Creek expansion over 30 years using 85.0 percent tax-exempt IRC Section 142(a)(5) Private Activity Bonds ($204,000,000 at 5.15 percent) and 15.0 percent private equity ($36,000,000 at 11.50 percent). The Unitary Availability Payment totals $49,042,569/year ($17,802,569 capital charge yielding 1.32x SPV DSCR, $29,440,000 O&M reflecting 8.0 percent efficiency, and $1,800,000 lifecycle MRA, with a $4,904,257/yr performance deduction cap):
| 30-Year Whole-Life PV Component (@ 4.60 percent) | Risk-Adjusted PSC (DBB) | Stack C: DBFOM P3 |
|---|---|---|
| Base Capital / Capital Availability PV | $240,000,000 | $286,602,981 (GASB 94) |
| Retained Construction Overrun Risk (14.0%) | $33,600,000 | $0 (Transferred) |
| Base O&M + Lifecycle Reserve PV | $544,145,109 | $502,931,751 |
| Retained Public O&M Drift Risk (5.0%) | $25,758,348 | $0 (Transferred) |
| Total 30-Year Whole-Life PV | $843,503,458 | $789,534,732 ($53,968,725 / 6.4 percent VfM) |
Under GASB Statement No. 94, a municipal availability-payment P3 is no longer off-balance-sheet: the utility records a financed-purchase liability equal to the present value of the capital charge ($286,602,981 at 4.60 percent). On the tax side, unlike airports and docks (IRC Section 146(g)(3)) or governmentally owned solid waste disposal facilities (IRC Section 146(h)), sewage exempt facility PABs under IRC Section 142(a)(5) remain subject to state volume cap under IRC Section 146 even when governmentally owned. Sponsors manage a $204,000,000 PAB issue through state volume cap allocation and multi-year carryforward elections (IRC Section 146(f)), carving out qualifying solid-waste/biosolids components under Section 142(a)(6)/146(h) where eligible, or pairing governmental tax-exempt bonds with an IRS Rev. Proc. 2017-13 DBOM contract (30-year / 80 percent life ceiling, zero net-profits sharing).
Benchmark Stack C against blended federal-muni financing in CWSRF, WIFIA, and blended municipal wastewater stacks, review industrial reuse project finance in water reuse project finance, DSCR, and PFAS rate covenants, and run your own VfM and GASB 94 calculation in the free Wastewater Project Finance and SRF Model (Excel).
No. Under GASB Statement No. 94, when asset ownership transfers to the utility by contract end, the capital component of the Availability Payment is booked as a financed purchase ($286,602,981 liability on Cedar Creek), while O&M and lifecycle fees are expensed as incurred.
Yes. Unlike airports and docks (IRC Section 146(g)(3)) or governmentally owned solid waste disposal facilities (IRC Section 146(h)), sewage exempt facility PABs under IRC Section 142(a)(5) require state volume cap allocation under IRC Section 146 even when governmentally owned. Sponsors address this through Section 146(f) carryforward elections, phased issuance across calendar years, or governmental-bond DBOM structures under IRS Rev. Proc. 2017-13.
Discounting the P3 Availability Payment at a higher private WACC while discounting the Public Sector Comparator at a lower municipal bond rate. Both streams must be discounted at the utility's identical tax-exempt borrowing rate (4.60 percent on Cedar Creek), with risk priced explicitly in cash flows.
This guide is drawn from The Wastewater Treatment Project Finance Handbook, following municipal treatment expansions, DBFOM P3s, and private industrial water reuse projects from NPDES permits through financial close.